Uttarakhand's

Uttarakhand's

There is a network of hydropower projects spread over the rivers of Uttarakhand. Along with 39 projects including Tehri, 32 small and big projects of UJVNL and Uttarakhand’s projects of various companies are also included in this.  Supreme Court has banned 24 projects

The government of Uttarakhand had approved more than two dozen hydroelectric projects between 2005 and 2010.

The completion of these projects costing thirty thousand crores will generate 2944.80 MW of electricity. The case of 24 small and big hydro projects by NGOs one by one reached the Supreme Court.

This case has also reached the NGT. The 12-member committee of experts was constituted by the Union Forest and Environment Ministry on the court’s order. After several months of study, the committee submitted its report to the ministry.

The report was submitted to the court on behalf of the ministry, after which the Supreme Court put a stay on these 24 projects.

These projects are on hold;

Bal Bal Ganga-2, Jhala Koti, Bhairav Valley, Jaldrigarh, Siangarh, Kakoragarh, Kotlibhel, Carmoli, Jadhganga, Rambara, Kotlibhel-2, Alaknanda, Khirrao Ganga, Urgam-2, Lata Tapovan, Malarizhelam, Jailmaktam, Tamkalaata, Bhayandarganga, Rishiganga-1, Rishiganga-2, Birhiiganga-1 and Gohna Tal.

3971 MW power is being built in these 39 Uttarakhand’s projects

Maneri Bhali Stage-2 – 304 MW
Chibaro – 240 MW
Ramganga – 198 MW
Chilla – 144 MW
Khodri – 120 MW
Tiloth – 90 MW
Dhalipur – 51 MW
Khatima – 41.4 MW
Dhakrani – 33.75 MW
Kulhal – 30 MW
Pathri – 20.4 MW
Mohammadpur – 9.3 MW
Galogi – 3 MW
Urgam – 3 MW
Dunav – 1.5 MW
Tanakpur – 120 MW
Dhauliganga – 280 MW
Tehri Dam – 1000 MW
Koteshwar Dam – 400 MW
Rajavakti – 3.6 MW
Hanuman Ganga – 4.95 MW
Vishnuprayag – 400 MW
Dewal – 5 MW
Loharkhet – 4.8 MW
Agunda Thati – 3 MW
Vanala – 15 MW
Bhilangana – 22.5 MW
Motighat – 5 MW
Birahiganga – 7.5 MW
Rishiganga – 13.2 MW
Bhilangana 3 – 24 MW
Gangni – 8 MW
Sarju Stage-3 – 10.5 MW
Badiyar-4.9 MW
Srinagar – 330 MW
Sarju Stage-2- 15 MW
Tanga – 5 MW
UJVNL. These projects are under construction
Vyasi – 120 MW
Lakhwar – 300 MW
Pala Maneri – 480 MW
Bhairon Valley – 381 MW
Bowla Nandprayag – 300 MW
Nandprayag Langasu – 100 MW
Tamak Lata – 280 MW
Government Bhayol – 120 MW
Sela Pithoragarh – 230 MW
Taluka Narrow – 140 MW
Rishiganga-1 – 70 MW
Rishiganga-2- 35 MW
Madmaheshwar – 15 MW

These are also Uttarakhand’s projects

Karligad – 9 MW
Kaliganga-2 – 4.5 MW Asiganga-
1 – 4.5 MW
Kaliganga-1 – 4 MW Sobla-
1 – 8
MW
Asiganga- 2 – 4.5 MW Dunav – 1.5 MW
Suvarigad – 2 MW
Limchagad – 3.5 MW
Tankul – 12 MW
Panagad – 4 MW
Yellowgad – 1 – 4 MW
Urgam – 2 – 3.8 MW Asiganga –
3 – 7.5 MW
Surigad – 2 – 5 MW
Sonagad – 3 MW
Bhilangana – 2A – 24 MW
Bhilangana – 2B – 24 MW
Bhilangana – 2C – 24 MW
Ongoing construction of these projects of big companies (THDC, NTPC, SJVNL)
Tehri PSP – 1000 MW
Tapovan Vishnugad – 520 MW
Vishnugad Pipalkoti – 444 MW
Lata Tapovan – 171 MW
Natwar Mori – 60 MW
Devasarbhi Dam – 252 MW
Kothi BHEL-1A – 195 MW
Rusia Bagar – 260 MW
Kothi BHEL-1B – 320 MW
Kothi BHEL-2 – 530 MW
Jakhol Narrow – 51 MW
Jhelum Tamak – 108 MW
Maleri Jhelum – 65 MW
Gohana Tal – 50 MW
Gauriganga-3A – 120 MW
Dhauliganga Intermediate Stage – 210 MW
Karamouli Pithoragarh – 55 MW
Chungar Pithoragarh – 240 MW
Garba Tawaghat – 630 MW
Karamouli Uttarkashi. – 140 MW
Jadhganga – 50 MW
Bokang Belling – 330 MW
Project
Rayat of Private Companies getting ready in Uttarakhand’s – 6 MW
Yundar Ganga – 24.3 MW
Phata Yung – 76 MW
Singoli Bhatwadi – 99 MW
Hanuman Ganga Extension-2 – 1.9 MW
Lagararu – 3 MW
Burthing – 6.5 MW
Fuliabagar – 5 MW
Balighat – 5.5 MW
Barnegad – 22.8 MW
Kot-Buudakeedar – 6 MW
Jhalakoti – 12.5 MW
Khirao Ganga – 4 MW
Devali – 13 MW
Calganga – 5 MW
Hanol Tuni – 60 MW Kakora
Gad – 12.5 MW
Jalandhari Gad – 24 MW
Siagad -11.5 MW
Alaknanda – 300 MW
Malkhet – 24 MW
Sarju Stage-1 – 7.5 MW
Khutani – 21 MW Rambara –
76 MW
Birahi Ganga-1 – 24 MW
Balgad – 19.80 MW
Madakini – 21 MW
Mori-Hanol – 63 MW
Rupin Stage-3 – 8 MW
Rupin Stage-4 – 10 MW
Birahi Ganga-2 – 24 MW
Urthing Sobla – 340 MW